Job Identifier |
|
Project Location |
Ordu / İzmir |
Project Work Group |
Super Structure |
Project Category |
Education Complex |
Project Scope Of Bid |
Turnkey Lumpsum |
The employer of the project, which was started on 10.08.2016 and completed on 16.04.2018, is the Presidency of Ordu University. The project consisting of 2 blocks with 5 floors; Reinforced Concrete Construction covers architectural and finishing works, electrical and mechanical works, infrastructure and landscaping works.
Project Information |
|
Date Of Contract |
08/10/2016 |
Date Of Completion |
04/16/2018 |
Completion Time |
614 Day |
Construction Area |
15.064 M2 |
In the Faculty of Dentistry consisting of 15.000 M2 closed area; It provides services in 8 departments, mainly Oral, Dental and Maxillofacial Surgery and Radiology, and Dental Diseases Treatment, Endodontics, Orthodontics, Pedodontics, Periodontology and Prosthetic Dentistry.