Loading...
Project Location        
Malatya / Turkey
Year of Construction
2020-2018
Project Work Group
Superior Structure
Project Category
Sports Complex

Employer

General Directorate Of Youth And Sports

Actual Status

Completed
Job Identifler
Project Location        Malatya / Turkey
Project Work Group Superior Structure
Project Category Sports Complex
ProJect Scope Of Bid Unit Price
Employer of the project for which the contract was signed on 18.07.2018 is the YOUTH and SPORTS MINISTRY. The project having tribune with the capacity of 2.500 audiences, two seperate tribune, ten diffirent swimline track with 50 meter length and 2,5 meter depth . Project includes basic structure, architectural and finishing works, electrical and mechanical works, infrastructure and environmental management, car parks and roads, structural and vegetal landscape works.

Project Information
Date Of Contract 18.07.2018
Date Of Completion 05.09.2020
Completion Time 780 Day
Total Length Of Line 16.500 m2
The seats of the new 2500-person swimming pool tribunes are integrated with Red - White Colors. The 50-meter-long swimming platform with 10 lanes is designed to host all kinds of Olympic competitions.