Project Location        
Elazıg / Turkey
Year of Construction
2001-2000
Project Work Group
Superior Structure
Project Category
Building Complex

Employer

T.J.K. Headquarters

Actual Status

Completed
Job Identifler
Project Location        Elazıg / Turkey
Project Work Group Superior Structure
Project Category Building Complex
ProJect Scope Of Bid Unit Price
The employer of the project, the construction of which was started on 13.08.2001 and completed on 18.12.2001, is the General Directorate of the Jockey Club of Turkey.

Project Information
Date Of Contract 13.08.2000
Date Of Completion 18.12.2001
Completion Time 468 Day
Total Length Of Line N/A
The project, which consists of the construction of barn, feed and warehouse works of Elazig Hippodrome, includes reinforced concrete construction, architectural and finishing works, mechanical and electrical works.