Loading...
Project Location        
Corum / Turkey
Year of Construction
1989-1985
Project Work Group
Infrastructure
Project Category
Drinking Water Networks

Employer

Iller Bank General Directorate

Actual Status

Completed
Job Identifler
Project Location        Malatya / Turkey
Project Work Group Infrastructure
Project Category Drinking Water Networks
ProJect Scope Of Bid Turnkey Lumpsum Price
The employer of the project, the construction of which was started in 1985 and completed in 1989, is the General Directorate of Iller Bank. Infrastructure includes drinking water line and connections.

Project Information
Date Of Contract 1985
Date Of Completion 1989
Completion Time 4 Years
Total Length Of Line N/A
POLYETHYLENE pipes, which are produced from HDPE plastic and whose pipe diameters vary between 300 and 2000 bars, were used in the project, which also has horizontal drilling transitions in city connections.