JOB Identifier |
|
Project Location: |
Cayırlı / Erzincan |
Project Work Group: |
Industrial Facilities |
Project Category |
Gas Production Plant |
Project Scope Of Bıd |
Turnkey Lump Price |
The main employer of the project, which was started on 01.12.2011 and completed on 28.02.2014, is BOTAŞ, and our main contractor and employer is TECNICAS REUNIDAS. The project, the construction of which was completed within the scope of the Baku-Tbilisi-Erzurum natural gas pipeline, which is a part of the 'NABUCCO PROJECT' signed in Ankara hosted by Turkey; 4 Gas Compressor Stations, 2 6-Storey Mission Residences, 1 Guest House, 1 Cafeteria, 1 Control Maintenance Building, 2 Main Security Buildings, 1 Gas Skid Building, 1 Generator Building It includes 1 Heating Center, 1 Closed Garage, infrastructure works, landscaping and vehicle passageways.
Project Information |
|
Date Of Contact: |
12/01/2011 |
Date Of Completion: |
01/25/2012 |
Completion Time: |
310 Day |
Treatment Capacity: |
2.000.000 m3/h |
The station completed in the project, which transports Caspian and Middle Eastern natural gas to Europe, will accelerate the flow of the existing natural gas line and make it regular and increase the capacity of our national natural gas line. The project, which has a capacity of 2 million m3 natural gas discharge per hour, was built on a 52.000 m2 land.