Project Location        
Konya / Türkiye
Year of Construction
2020- 2016

Client:

3rd Regional Directorate of Highways

Current Status:

Completed
Job Identifier
Location                 Konya / Türkiye
Group                     Highways & Railways
Sub Category        Highway
Proposal Type      Unit Price
The contract for the project was signed on 20.08.2016, with the 3rd Regional Directorate of Highways in Konya as the client. The project was carried out in three phases, covering kilometers 18-23, 33-55, and 65-93, and included earthworks, engineering structures, superstructure, and hot mix asphalt paving.

Project Information
Contract Date       20.08.2016
Completion Date 10.12.2020
Length                     93.000 M
Capacity                 Not available
The 93 km long divided highway, connecting Konya and Beyşehir, was completed and opened to traffic as a dual carriageway with a total width of 12 meters.