Loading...
Project Location        
Orhaneli / Bursa
Year of Construction
2011-1999
Project Work Group
Water Structures
Project Category
Dams And Pods

Employer:

D.S.I. 1. Regional Directorate

Actual Status:

Completed
Job Identifier
Project Location Orhaneli / Turkey
Project Work Group Water Structures
Project Category Dams And Pods
Project Scope Of Bid Offer Unit Price
The employer of the project, the construction of which was started on 11.02.1999 and completed on 03.01.2011, is the State Hydraulic Works. It covers spillway and body construction works.

Project Information
Date Of Contract 02/11/1999
Date Of Completion 01/03/2011
Completion Time 11 Years
Pond Capacity 865.000 M3
It was built for irrigation purposes on the Bozönü Stream, which flows into the Orhaneli Stream, within the borders of the Karncalı town of the Orhaneli District. The pond dam, the construction of which was started in 1999, is of the zoned earth fill type and the fill volume is 0.355 hectometers, and its height from the foundation is 31 meters. The pond, which has a water capacity of 0.865 cubic meters, is expected to irrigate 308 hectares of agricultural land.